Today we meet with Gerry and NCC staff member to clarify windmill design.
Outcome of todays meeting -
-Need to do test drill in earth.
-Order metal and wood
-Risk assessment (draft) has been emailed to Gerry.
-Possible issues with drilling holes, this is currently being discussed with fencer.
-Does anyone own a saftey vest, could they bring it with them to site next week.
-Ann to collect witches hats and bunting on Wed 5pm from shopfront at Hunter Street.
Important Dates
1. Windmill construction session this Friday at Varelle's place at 1.30pm.
2. Bump in Monday 9am, need to measure out distance between windmills, may be able to do this Sunday? Mark earth with spraypaint.
Monday, January 14, 2008
Subscribe to:
Posts (Atom)